Wild Dunes - Isle of Palms Beach Renourishment
Here is the latest news from Wild Dunes as it relates to the beach renourishment project:
We have Bulldozers, heavy equipment, pipe and personnel on the beach NOW & will start pumping sand soon
2008 Beach Restoration Project
PROJECT SUMMARY
The northeastern end of the Isle of Palms has been enduring a severe erosion crisis as a shoal attaches to that section of the island. If the current episode continues unabated, structures could be threatened. In order to protect the public safety and to ensure that the beaches remain healthy, the City has undertaken a beach nourishment project scheduled to occur in the spring and summer of 2008. The South Carolina Department of Health and Environmental Control office of Ocean and Coastal Resource Management (SCDHEC OCRM) has issued the City a permit that stipulates "up to 885,000 cubic yards of sand will be dredged from four offshore borrow sites and pumped via hydraulic pipeline to renourish 13,785 linear feet of beach." This project will restore the dry sand beach, control the erosion and include the removal of all sandbags currently placed in the erosion area.
ANSWERS TO PROJECT QUESTIONS
When will the project start?
Soon, but the exact start date is still undecided as the final steps are taken in the preparation and permitting process. Weeks Marine, the company that will perform construction, has mobilized their equipment. Any day now, beach goers may notice equipment on the beach.
When will the project end?
July 31, 2008.
Where will the project start and end?
The beach to be restored runs from
What about the sea turtles th! at ne st on the Isle of Palms?
The City has been working closely with all appropriate local, state and federal agencies to ensure maximum protection for sea turtles. The permits issued by the agencies allowing construction to occur include clear guidelines to protect sea turtles. Every night and every morning, turtle monitors will walk the construction area looking for turtles and their tracks, and if one is found, the appropriate steps will be taken to protect the turtle and its nest.
Will the project run all day and night?
Yes. The project will run 24 hours per day and 7 days per week, even on Memorial Day and July 4th. The goal is to complete the project as soon as possible, so unless inclement weather forces a delay, construction will continue all the time.
What will construction be like?
Beach restoration is a large project that involves an off-shore dredger, large pipeline and heavy equipment and truck! s. Vi sitors and residents in close proximity to the project can expect to see this large equipment and hear noise. At night, lights will illuminate the beach so construction can continue. These disruptions will be temporary as the project moves down the beach.
Will the beach be closed?
The beach to be restored is approximately 9,200 feet long, but only a section of the beach will be under active construction on any given day. The section under construction will be clearly marked and closed to visitors. The rest of the beach will be open as usual. Also, the construction will be progressive, meaning it will move along the beach during construction.
Will the project affect boaters?
Boaters needs to be aware that pipeline, marked with buoys, will be submerged in the waters around the project.
What about the sandbags?
By the end of the project, all the sandbags will be removed from the beach.
What will the beach be like with the project is completed?
The goal of the project is to restore a dry sand beach.





















